| 
FERC
Responds Positively to Chelan P.U.D. Rehearing Request on Cost
Cap and Project Boundary Issues
By
Daniel
M. Adamson, Brian
Gish and Lisa
B. Zycherman
On April 19, 2007,
the Federal Energy Regulatory Commission (FERC) granted rehearing
in part to the Public Utility District No. 1 of Chelan County,
Washington (“District”) of the Nov. 6, 2006 Commission
staff order issuing a new license for the 48-megawatt Lake Chelan
Hydroelectric Project (“Project”). The rehearing
order includes improvements in the Commission’s treatment
of license article cost-caps arrived at as part of negotiated
relicensing settlements. The cost-cap issue has been a major
issue for licensees who have negotiated cost-caps on certain
obligations with agencies and stakeholders which have then been
overridden by the Commission.
In the rehearing
order, the Commission affirmed its authority to “add provisions
that are supplemental to, or more stringent than, the mandatory
conditions,” to ensure that cost capping provisions for
funding conditions do not render implementation of a needed
measure “incomplete.” However, FERC agreed with
the District’s argument that any exercise of FERC’s
authority to require a licensee to surpass cost caps must be
subject to notice and opportunity for hearing. Accordingly,
FERC modified Article 402 of the District’s new license
to explicitly include notice and opportunity for hearing for
any changes to funding levels for specific measures. This change
will provide the District a valuable tool for preserving the
benefits of the cost caps it negotiated as part of its relicensing
settlement.
In addition, FERC
agreed with the District that when a settlement cost cap is
included in a mandatory license condition that FERC determines
is not in the public interest under Section 10(a)(1) of the
Federal Power Act (FPA), the reservation of authority in Article
402 does not apply to those cost caps. The District had argued
that if the Commission believed a license measure was not in
the public interest there was no reason for the Commission to
reserve its authority to require a licensee to spend more on
such a measure. FERC agreed. In the case of the Lake Chelan
Project new license, this is a significant change because the
Commission held that a number of the license articles included
as mandatory FPA Section 4(e) were not in the public interest
under Section 10(a)(1). Consequently, the spending limits in
these articles are now “hard caps.”
FERC’s Order
also addressed several Project lands issues raised by the District.
With respect to wildlife habitat lands, FERC denied rehearing
on the District’s request that Article 406 of the new
license be revised to delete a provision for bringing lands
requiring ongoing maintenance to ensure the success of wildlife
habitat measures into the Project boundary. The Commission stated
that it retained the authority to bring such lands within the
Project boundary, even if the lands at issue are not “contiguous
with the project or are located some distance from the project.”
However, the FERC clarified that it “generally do[es]
not require lands on which one-time measures are implemented
to be included within project boundaries.”
Finally,
FERC affirmed the conclusion in the original license order that,
given the value of whitewater resources associated with the
Project, a three-year whitewater conditions monitoring study
in an extremely hazardous river reach may not be indefinitely
delayed while the District seeks to resolve liability concerns.
Consistent with its relicensing settlement agreement the District
had sought to delay the whitewater releases and monitoring study
until it had obtained liability insurance or until an applicable
state statute had been amended to include an extension of immunity
protections for recreational whitewater releases.
For
more information, please contact:
This
advisory is a publication of the Energy Department of Davis
Wright Tremaine LLP. Our purpose in publishing this advisory
is to inform our clients and friends of recent developments
in energy law. It is not intended, nor should it be used, as
a substitute for specific legal advice as legal counsel may
only be given in response to inquiries regarding particular
situations.
Copyright
© 2007, Davis Wright Tremaine LLP.
return to Advisory Bulletins main page
|