Energy Advisory Bulletin
California Government Reorganization
Commission Rejects Schwarzenegger Energy Agency Reorganization Plan
By Chris
Hilen
[June 2005]
California Governor Arnold Schwarzenegger’s
energy agency reorganization plan (Reorganization Plan) suffered
a setback on June 23, 2005. The California Commission on California
State Government Organization and Economy (commonly referenced as
the “Little Hoover Commission” or the “Commission”)
recommended that the California Legislature reject the Governor’s
plan to restructure California’s multiple energy agencies.
The Governor submitted the Reorganization Plan, A
Vision for California’s Energy Future, to the Little Hoover
Commission on May 12. He submitted a revised version of the Reorganization
Plan on June 13, and at the same time submitted the Reorganization
Plan and implementing legislation to the Legislature.
The Little Hoover Commission based its
recommendation against the Reorganization Plan on two legal opinions
issued by the California Attorney General and one legal opinion
issued by the Legislative Counsel of California. Those legal opinions
concluded that several elements of the Reorganization Plan are “illegal”
on the basis that they impermissibly transfer from the California
Public Utilities Commission (CPUC) to the proposed new State Department
of Energy (Department) ratemaking powers and functions that are
conferred on the CPUC by the California Constitution. The legal
opinions reasoned that functions that are conferred on a state agency
by the Constitution cannot be transferred to a different agency
through the governmental reorganization process; such transfers
require constitutional amendment. The Commission stated that if
the Reorganization Plan were allowed to go into effect “it
would be subject to legal challenge.”
Little Hoover Commission Endorsed Many Elements of Reorganization
Plan
The Reorganization Plan establishes a
State Department of Energy that would be responsible for the state’s
energy policy and a significant number of related functions. The
Department would be headed by a Cabinet-level appointed Secretary
of Energy who reports directly to the Governor. The California Energy
Commission would remain in existence, with the Secretary of Energy
serving as its Chairperson. The remaining Energy Commission members
would serve staggered four-year terms appointed as they are now
by the Governor subject to confirmation by the California State
Senate. The president of the CPUC and the president of the California
Independent System Operator (CAISO) would sit as ex-officio
non-voting members of the reformed Energy Commission.
Under the Reorganization Plan, most of
the current functions of the Energy Commission would be assumed
by the new Department of Energy, including its energy analysis and
strategic planning functions. The Energy Commission, as a component
of the new Department, would retain its authority for the permitting
of power plants that are 50 MW or larger. The California Power Authority
and the California Electricity Oversight Board would each be eliminated.
A new Office of Energy Market Oversight (OEMO) within the Department
would perform electricity market monitoring and oversee the CAISO.
The Little Hoover Commission found no
legal fault with these organizational changes and recommended the
creation of a State Department of Energy as an important step toward
improving “leadership and accountability” in the state’s
efforts to ensure safe, clean, affordable and reliable energy. The
Commission encouraged the Governor to resubmit the Reorganization
Plan with these provisions.
Similarly, the Commission found no legal
impediment to the following elements of the Reorganization Plan:
- Provision to the OEMO of shared responsibility with the CPUC
for representing California before the Federal Energy Regulatory
Commission (FERC) and exclusion of all other state agencies and
offices from representing the state before FERC. The original
Reorganization Plan would have also eliminated the CPUC’s
role and made the OEMO the state’s exclusive representative
before FERC. (Under the present practice, it is not uncommon for
up to half a dozen California regulatory agencies and executive
offices to file separate pleadings, often advocating different
positions “on behalf of the People of State of California”
with the FERC).
- The transfer to the Department of responsibility for certification
of non-utility owned natural gas transmission pipelines and storage
facilities. In another change from the original Reorganization
Plan, this provision does not remove the CPUC’s historic,
constitutionally-mandated responsibility for issuing CPCNs for
utility-owned natural gas facilities.
- The transfer from the CPUC to the Department of responsibility
for determining whether construction of proposed new electric
transmission lines is necessary to facilitate achievement of the
state’s renewable power goals.
Three Elements of Reorganization Plan Are Subject to Legal
Challenge
The Little Hoover Commission recommended
against approval of the Reorganization Plan, based on the legal
opinions by the Attorney General and the Legislative Counsel. These
legal opinions collectively concluded that three elements of the
Reorganization Plan illegally transfer from the CPUC to the Department's
constitutionally-conferred utility ratemaking functions:
- It unlawfully deprives the CPUC of the responsibility for issuing
CPCNs for utility-owned electric transmission facilities. Certification
of utility-owned electric facilities is an integral part of the
CPUC’s utility ratemaking functions (as noted above, the
revised Reorganization Plan leaves the CPUC with authority for
issuing CPCNs for utility-owned natural gas facilities).
- It unlawfully deprives the CPUC of its existing responsibility
for making statutorily-required cost recovery determinations for
utility infrastructure projects on which the CPUC issues CPCNs.
These cost recovery determinations are integral to the CPUC’s
ratemaking function.
- It unlawfully transfers to the Department the CPUC’s
current responsibility for ensuring the electric transmission
rates established by FERC are fully reflected in any retail rates
established by the CPUC. The flowing through of wholesale transmission
rates is an explicit ratemaking function conferred on the CPUC
by the California Constitution.
Reorganization Plan Becomes Law Unless Rejected by the
State Legislature
Under California’s governmental
reorganization process, the Reorganization Plan cannot be amended
by the Legislature, which may only reject it or let it become law
in its entirety. If neither body of the Legislature rejects the
Reorganization Plan within 60 days of its submission to the Legislature,
the energy agency reorganization will become operational by law.
The deadline for either the State Assembly or the State Senate to
reject the Reorganization Plan is September 12 (the days of the
Legislature’s recess from July 15 to August 15 are not included
in the 60-day period).
This Advisory is a publication of the Energy Department of Davis Wright Tremaine LLP. Our purpose in publishing this Advisory is to inform our clients and friends of recent developments in energy law. It is not intended, nor should it be used, as a substitute for specific legal advice as legal counsel may only be given in response to inquiries regarding particular situations.
Copyright © 2005, Davis Wright Tremaine LLP.
return to Advisory Bulletins main page
|